On May 6, 2022 at 14:22, westcojack said...
Vantage as well as many other control companies are having issues obtaining chips.
While we understand Lutron has an 18 month backlog on many items, Vantage is 10-16 weeks.
Does anyone know about deliveries for Control4 or Savant or Crestron?
Place orders asap to get early delivery, I foresee many jobs at a standstill.
Crestron is pretty much running at 12+ week lead time for some items and 26+ weeks for others.
I emailed our contact for supply questions and was informed that amplifiers are 26 week lead times.
Keypads we ordered in February/March of this year isn't expected to ship until Jan 2023.
Shades are shipping late September/early October
Processors, centralized lighting is 12-16 weeks