westcojack Long Time Member |
|
|
Vantage as well as many other control companies are having issues obtaining chips. While we understand Lutron has an 18 month backlog on many items, Vantage is 10-16 weeks. Does anyone know about deliveries for Control4 or Savant or Crestron?
Place orders asap to get early delivery, I foresee many jobs at a standstill.
|
Jack Goldberg, PE |
|
Post 2 made on Friday May 6, 2022 at 16:23 |
Proggieus Long Time Member |
Joined: Posts: | October 2005 434 |
|
|
Crestron
so long as you don't have any work before Christmas you might be OK-
We luckily saw this coming a bit and ordered what we felt would be about a 6 month supply of our most often used SKUs that are starting to trickle in and have then been placing replacement orders as new jobs get approved.
|
|
Post 3 made on Saturday May 7, 2022 at 20:36 |
Greg C Super Member |
Joined: Posts: | October 2002 2,588 |
|
|
We had to add Savant to our lineup. They have been able to deliver processors and remotes.
|
CEDIA University Designer CAT Team Member CEDIA University Instructor CEDIA Registered Outreach Instructor |
|
Post 4 made on Monday May 9, 2022 at 12:19 |
rlustig Advanced Member |
Joined: Posts: | June 2004 915 |
|
|
Control4 is ok on stock/deliveries. EA controllers are in stock, amps are pretty much in stock, Matrix switches have been backordered for months. Remotes are ok. Projects can get going, not necessarily finished. Panelized lighting is hit or miss. Enclosures and adaptive phase dimmer modules are in stock, forward phase and relay modules backordered.
|
|
Post 5 made on Monday May 9, 2022 at 20:09 |
joelusi Long Time Member |
Joined: Posts: | October 2011 370 |
|
|
No issues with URC here. Able to get all Total Control equipment
|
|
Post 6 made on Wednesday May 25, 2022 at 16:16 |
SWOInstaller Select Member |
Joined: Posts: | October 2010 1,595 |
|
|
On May 6, 2022 at 14:22, westcojack said...
Vantage as well as many other control companies are having issues obtaining chips. While we understand Lutron has an 18 month backlog on many items, Vantage is 10-16 weeks. Does anyone know about deliveries for Control4 or Savant or Crestron?
Place orders asap to get early delivery, I foresee many jobs at a standstill. Crestron is pretty much running at 12+ week lead time for some items and 26+ weeks for others. I emailed our contact for supply questions and was informed that amplifiers are 26 week lead times. Keypads we ordered in February/March of this year isn't expected to ship until Jan 2023. Shades are shipping late September/early October Processors, centralized lighting is 12-16 weeks
|
You can't fix stupid |
|
Post 7 made on Friday May 27, 2022 at 10:41 |
SWFLMike Long Time Member |
Joined: Posts: | January 2007 356 |
|
|
On May 25, 2022 at 16:16, SWOInstaller said...
Crestron is pretty much running at 12+ week lead time for some items and 26+ weeks for others. Shades are shipping late September/early October Processors, centralized lighting is 12-16 weeks I ordered a couple shades at the beginning of March and got the estimate that they'd arrive in October. I just got the shipping notification this morning that they're on the way. Processors are taking a long time still. Ordered an MC4 about 2 months ago and they said it'll be here next month. Not holding my breath!
|
|
Post 8 made on Friday May 27, 2022 at 11:19 |
BHuey1969 Long Time Member |
Joined: Posts: | September 2016 198 |
|
|
No real issues with Savant, URC (CCP), RTI, or Pro Control. I know most of you guys are not fans of any of these, but we gotta sell something right?
|
|
Post 9 made on Monday May 30, 2022 at 09:17 |
Dawn Gordon Luks Founding Member |
Joined: Posts: | September 2001 1,178 |
|
|
Hunter Douglas is running at 6 weeks and Lutron 4-5 weeks for shades.
|
|
Post 10 made on Monday May 30, 2022 at 22:09 |
Stryker Long Time Member |
Joined: Posts: | November 2010 402 |
|
|
It’s totally fabric dependent. Lutron blackout value premiere is at 60 business day lead time right now. It changes a lot but most standard fabrics other than blackout are 20-30 business day lead time
|
"If they give you ruled paper, write the other way" |
|
Post 11 made on Tuesday June 14, 2022 at 03:26 |
Gman Select Member |
Joined: Posts: | February 2009 2,244 |
|
|
We ordered Crestron Home processors in October 2021 and still haven’t received. Are you Crestron dealers looking at other control systems to fill your orders? We receive some equipment and pay for it but have then sit on it until the balance of product comes in. Very frustrating
|
|
|
Post 12 made on Tuesday June 14, 2022 at 08:44 |
lippavisual Senior Member |
Joined: Posts: | December 2007 1,463 |
|
|
Extron is about 10-12 weeks out on anything that requires a processor chip, including Dante anything. It's definitely put a lot more strain on our schedules trying to finish up projects, get paid and move on!
Let alone the cost increases on everything.
|
|
|
Post 13 made on Tuesday June 14, 2022 at 10:38 |
ichbinbose Select Member |
Joined: Posts: | August 2011 1,824 |
|
|
Elan is doing ok right now. I just placed a PO for a system. Processor, Dante based matrix amp, touchscreen & remotes. I also managed to order several ubiquity edge switch’s, that happened to show in stock on Sunday.
|
|
Post 14 made on Tuesday June 14, 2022 at 16:32 |
johnmax Long Time Member |
Joined: Posts: | June 2004 187 |
|
|
On June 14, 2022 at 03:26, Gman said...
We ordered Crestron Home processors in October 2021 and still haven’t received. Are you Crestron dealers looking at other control systems to fill your orders? We receive some equipment and pay for it but have then sit on it until the balance of product comes in. Very frustrating Some jobs we have had to use Savant instead which isnt as bad as Crestron with equipment timeframes. We are mainly a custom non-Crestron Home dealer though so it sucks to use Savant instead of our main offering.
|
|
Post 15 made on Wednesday June 15, 2022 at 13:52 |
Gman Select Member |
Joined: Posts: | February 2009 2,244 |
|
|
On June 14, 2022 at 16:32, johnmax said...
Some jobs we have had to use Savant instead which isnt as bad as Crestron with equipment timeframes. We are mainly a custom non-Crestron Home dealer though so it sucks to use Savant instead of our main offering. How long is the programming learning curve for Savant? Was talking to my Crestron rep this morning and he was saying if you’re ordering CLX lighting right now it will be a year before you see it. Yikes
|
|
|
|
Before you can reply to a message... |
You must first register for a Remote Central user account - it's fast and free! Or, if you already have an account, please login now. |
Please read the following: Unsolicited commercial advertisements are absolutely not permitted on this forum. Other private buy & sell messages should be posted to our Marketplace. For information on how to advertise your service or product click here. Remote Central reserves the right to remove or modify any post that is deemed inappropriate.
|
|