1/2 hour for 2 techs seems extremely low in my eyes for a drop location.
I think in actuality I am running at twice that estimate and I misread my own spreadsheet. It should be 1/2 hour for two techs in parallel.
I arrived at this by looking at a full day where I estimate two techs can do around 15 locations with two cables. (Video locations take longer on average because we pull 6 cables and so cannot group up runs.)